Six Weeks Means Six Weeks: Quoting Stonework When the Load Slips
Photo: Acabashi, CC BY-SA 4.0, via Wikimedia Commons
There is a particular silence that settles on a job when the stone hasn't turned up and nobody wants to say whose fault it is. The scaffolder is stood down, two lads are sweeping a floor that was clean yesterday, and the client is asking - politely, twice a day - whether the kitchen fitters should still come Monday.
Nine times out of ten the stone arrives. Eventually. The trouble isn't the delay itself, it's that the quote you wrote in March assumed the delay wouldn't happen, and nobody priced the waiting.
Where a slipped load actually costs you
Split it into four lines, because they behave differently.
Standing time. A three-man gang at £780 a day doesn't stop costing money because there's nothing to lay. They either go home (and you pay them anyway, or you don't and you lose them to someone who will) or they get shuffled onto another job that then runs late too.
Programme knock-on. Scaffold on weekly hire, a skip on a daily rate, plant you're still paying for, a site cabin, the client's own trades booked in behind you. None of that cares that the quarry had a wet fortnight.
Storage and handling. Stone that turns up in three part-loads instead of one clean delivery costs more to receive, more to shift and more to protect. It also gets chipped more, because it's being handled four times instead of once.
Your own hours. Re-planning, phone calls, a re-issued programme, a difficult conversation. Call it a day and a half of your time. That's real money even if it never appears on an invoice.
A worked example
Say the job is 22 m² of Bath stone ashlar cladding plus a shaped fireplace surround, quoted at £18,400 with a margin of about 20% - roughly £3,700 in it for you. The quarry quotes six to eight weeks. You price on six, book the gang for week seven, the scaffold for week six, and the client books their kitchen fitters for week nine because you told them it'd be tight but fine.
The load lands in week eleven.
Two lost days for a gang of three at £780: £1,560. Scaffold standing an extra three weeks at £210 a week: £630. One extra skip swap and a bit of yard storage: £180. Your own re-planning time: £300. You're at £2,670 - and that's before the client starts muttering about the kitchen fitters.
That is most of the profit on the job, gone, for a delay that wasn't your fault and that you had absolutely no control over. All you can control is whether the quote says what happens next.
Date the price, not just the job
Stone moves. Quarry lead times shift with weather, capacity and their own order book, and imported material moves with shipping schedules and container costs. A quote that holds a price for six months is a quote that's quietly agreeing to absorb every increase in between.
Twenty-eight days is a normal, defensible validity period for a domestic job. Sixty days for a commercial one, if the main contractor wants it. Say it plainly on the quote, near the total, not buried in the small print on page four.
Treat delivery as an estimate, not a promise
This is the one clause that does the heavy lifting. You don't need to sound difficult - you need to be clear that the quarry's date is the quarry's date, and that your programme is built on an assumption.
Something along these lines:
Supplier lead times are given in good faith but are not guaranteed. The programme below assumes stone on site by [date]. Should delivery be delayed beyond 10 working days of that date for reasons outside our control, standing time will be charged at £[x] per operative per day and the programme will be re-issued.
That is fair, it is specific, and it gives you something to point at rather than something to argue about.
Deposits and stage payments that follow events, not dates
If you tie payments to calendar dates, a slipped load means you're chasing an invoice the client thinks you haven't earned. Tie them to things that actually happen instead:
- 30% on order, to secure the stone and cover the quarry's own deposit
- 40% on delivery to site, signed for
- 30% on practical completion
Note that once stone is cut to size, it's yours and it's not going back. Say so, and make the deposit non-refundable at that point. If you're working for a domestic client, keep the wording plain and fair - the Consumer Rights Act 2015 expects services done with reasonable care and skill and terms that aren't weighted against them. Clear is better than clever here; a client who understands the terms doesn't argue about them later.
Substitutions: agree them before the saw starts
The other half of the delay problem is the supplier ringing you in week five to say the specified bed isn't available but they've got something 'very similar'. Sometimes it is similar. Sometimes it's a different colour, a different porosity and a different price, and you find out when it's on the wall.
One line covers it: No substitution of specified materials will be made without written agreement before cutting commences. Then, if it does happen, you have a documented conversation instead of an awkward one three weeks later.
Where the flexibility goes
None of this means being rigid. A client who's been kept informed will forgive a fortnight's delay far more readily than one who finds out on the day. Ring them when you hear, not when they ask. Offer a revised date and a revised sequence. Hold the price where you reasonably can, and be explicit when you can't.
The difference between a firm quote and a hostile one is whether the client feels the risk is being shared or dumped. Name the risk, price the risk, then get on with the job - and if the load does turn up late, at least the waiting is on the invoice rather than on your margin.